- Demolition and removal of all stucco over second-floor exterior framed walls
- Repair all wood frame dry rot on the second floor
- Installation of new WRB (Weather Resistant Barrier) concealed barrier components
- Properly integrate all WRB components with windows, roof components, and other penetrations
- Installation of new fiber cement siding with James Hardie Lap Siding
- All windows flashed in place and integrated with new WRB components
- Application of a Florida Paint quality acrylic paint system to all buildings
- New hurricane shutter bolts installed
- Replaced selectively failing lower back & front roofs, properly integrating with new WRB at roof to wall transitions